Barking Central

Housing (inc mixed use)
Barking, United Kingdom
Allford Hall Monaghan Morris
2010
World Architecture Festival 2010 - Category Commendation

View from public square to framed arboretum 
Timothy Soar 


The regeneration of Barking began over 9 years ago and the history of the project forms part of the ambitious regeneration of Barking as a key town in the Thames Gateway. From 2000, a number of proposals were developed for the site with AHMM were appointed to masterplan the area in 2002. The site and town centre as a whole has a rich history, transforming from agricultural land to the location of a range of industrial uses such as a Rope Works, R Whites Soft Drinks Factory, and Piano Factory. As the town centre evolved, this site became the civic heart of the town, holding the Town Baths, The Magistrates Court, and later the Town Hall and the Municipal Library.

As with all large scale urban regeneration projects, the client group is a complex mixture of local authority, community organisations and developers and AHMM worked hard to ensure that the vision for Barking Central was lost in this mix. As well as the London Borough of Barking and Dagenham (LBBD), the design team dealt with the following authorities; London Thames Gateway Development Corporation, GLA, Design for London, and CABE; organisations including Barking College and University of East London, and the developer
client Redrow Regeneration.

The land owner for the development throughout the process was the LBBD who worked in partnership with the private developer (originally Urban Catalyst and then Redrow Regeneration). In return for allowing the developer to implement the delivery of over 500 market sale residential units on the LBBD land, the developer was obliged to create a number of affordable residential units, to create a new Life Long Learning Centre (within the fabric of the existing library), and to spend over £1m on ‘public art’.

Barking Central is one of the most successful regeneration projects in the UK.
It has revitalized Barking town centre with a large mixed-use scheme of 7 new buildings including a new Learning Centre, over 500 residential apartments, a 66 bed hotel, a bicycle shed for 250 bikes, 9 retail units, a café, and new public spaces. Delivered in two phases over 9 years, AHMM masterplanned and designed the buildings overcoming many challenges to create a scheme that symbolizes the regeneration of this Thames Gateway town.

Phase I of the development included the creation of the new Barking Learning Centre and the Rope Works with over 250 apartments and a public square, located opposite the existing Town Hall. The key construction challenge was the retention of the original 1970s library building and the design of a new concrete frame and transfer structure built over library to support the 2 new linear buildings and Sky Garden above. Amazingly, Phase I was delivered four months early and within budget.

Phase II included a hotel, retail units, a grand bike shed and 3 residential buildings – Bath House, Lemonade Building and Axe House. The masterplan was deliberately designed with buildings of varying forms, heights and materials, connected by a colour strategy. Bath House has 96 1 and 2 bedroom apartments, most of which overlook the Aboretum and Town Square. Lemonade Building takes the form of a tower, enclosing the west end of The Arboretum. Its height responds to the tower of the Town Hall and signals the regeneration of the town centre. Seventeen storeys high, the building accommodates 68 1 and 68 2 bedroom apartments, all with terraces inset to provide more sheltered spaces. Axe Street houses 40 1 to 3 bedroom apartments, which sits to the south of the main buildings, designed as a white, neutral addition to the townscape.








Identity and Colours

The site and town centre as a whole has a rich history, transforming from agricultural land to the location of a range of industrial uses such as a Rope Works, R Whites Soft Drinks Factory, and Piano Factory. As the town centre evolved, this site became the civic heart of the town, holding the Town Baths, The Magistrates Court, and later the Town Hall and the Municipal Library.

AHMM worked with long term collaborator Studio Myerscough to develop branding and colour strategies for the whole scheme using references and inspiration from Barking’s rich past. Each building has been given a name that relates to previous industrial uses of the site. The bold use of yellow and green on the facades of Phase 1 is carried through to the interior of the Learning Centre, enlivened by a yellow floor, green furniture and large supergraphics. Over Phase 2, this developed further into a spectrum

Construction
On Phase I due to the need to simultaneously construct the residential blocks while work continued on the library below, modular construction principles were adopted from the outset to allow for ease of fabrication, installation and maintain programme and cost control. Apartment sizes and layouts were also developed to utilize an insitu cast concrete frame with flat slabs and blade columns. This minimized offset concrete frame components and limited the different type of units, which result in easy duplication of the separate building elements and a seamless floor on floor construction process.

Sustainability
The project makes a contribution to reducing climate change in a variety of ways, devised as a car free project it makes the most of its proximity to the excellent transports connections Barking offers, green roofs assist with insulation whilst reducing flood risk in an urban environment, the buildings white colour helps to prevent overheating and some of the flats have solar thermal renewable technologies. Phase 2 will bring the addition of a purpose built bike storage facility.

Now completed, Barking Central has created a vibrant, dense and high quality townscape that has reconnected parts of Barking, with active ground floor street edges, public amenities such as the Learning Centre, set around new public spaces. The scheme sets a new standard for future urban regeneration, and the following projects in Barking Town Centre.

Lead Architect »

Allford Hall Monaghan Morris
 

Professional Credits »

Client / Developer
London Borough of Barking & Dagenham
United Kingdom

Client / Developer
Mr Peter Green
Redrow Regeneration (Barking) Ltd
United Kingdom
01604 601 115
peter.green@redrow.co.uk

Environmental Engineer
Mr Dr Bernardo Vazquez
Buro Happold (COSA Solutions)
United Kingdom
0113 204 2200
bernardo.vazquez@burohappold.com

Landscape Architect
Mr Andrew Grant
Grant Associates
United Kingdom
01225 332 664
ag@grant-associates.uk.com

Main Contractor
Mr Colm Gallagher
Ardmore Construction Ltd
United Kingdom
020 8477 4785
cgallagher@ardmoregroup.co.uk

Project Manager
Baques Nigel Rose (Phase 2)
United Kingdom

Project Manager
Gill Associates (Phase 1)
United Kingdom

Public Realm Architect
Ms Liza Fior
muf architecture
United Kingdom
020 7251 4004
studio@muf.co.uk

Structural Engineer
Mr John Cunningham
Beattie Watkinson (Phase II)
United Kingdom
020 8834 1632
london@beawat.co.uk

Structural Engineer
Mr Andrew Best
Buro Happold (Phase 1)
United Kingdom
andrew.best@burohappold.com